McMahon Services - Homepage
 
     
 

PROJECT: Woomera Projects

Logos
 
 
aircraft
Aircraft on tarmac Old Fuel Farm
New Fuel Farm
New Fuel Farm
Tower
Replacement of asbestos
Building new bitumen aprons
Building new bitumen aprons

McMahon Services have recently completed Stage 2 at Woomera, this being one of a number of projects carried out over the past 2 years.

STAGE 1 REFURBISHMENT OF INFRASTRUCTURE

The refurbishment of infrastructure entailed asbestos removal, refurbishment of buildings and some demolition.

RANGE ‘E’

Range E is 40km west of Woomera on the prohibited area, and was detailed to have a number of redundant buildings demolished. This entailed, in some instances, the removal of asbestos materials prior to demolition.

TECHNICAL AREA AERODROME

Taxiways on the air strip from the existing runway back to the aprons of the facilities were rebuilt. This included building a new bitumen apron for the parking of planes in front of hanger No3 as well as the demolition of some buildings in the Technical Area. Also some asbestos removal work was done on the external faces of the existing control tower. This tower was totally refurbished with new Colourbond sheeting to the external walls. A 25KVA emergency generator was installed along with associated switchboards and electrical wiring for emergency lighting. All internal wiring was removed and replaced with new distribution boards on each level. Painting was carried out within the entire tower including amenities area at ground level along with the services parking bays. The existing fencing around the air strip was removed and replaced with new cyclone mesh fencing for security purposes. A new fuel farm was built to replace the old redundant system including new tanks, a building structure over the tanks, along with the pumps, filter and pipe work. All this was incorporated into a fenced compound. A new fire sprinkler system was installed within the hangers along with a new diesel pump and storage tanks for fire fighting purposes. A fire detection system was also installed within the ARDU building and interconnected to the Woomera Emergency Services. New bitumen roads were built within the Technical Area to provide access to all of the infrastructure.

WOOMERA VILLAGE

Demolition took place to the old swimming pool which had been replaced with a new one. Also new fire detection systems were installed in a number of buildings in the shopping centre complex and accommodation blocks.

PORT AUGUSTA TO WOOMERA PIPELINE

Repairs were carried out in some sections of the pipe line to replace the pipe supports, including new corrosion protection to the steel pipe work. New concrete culverts were installed on Range 'E' pipe line and earth embankments to provide access for the pastoralist over the above ground pipework.

RANGE E I.B. BUILDING

This building, which is located 40km west of Woomera on the prohibited area, was scheduled to be totally refurbished. Four outbuildings, used by the Department of Defence for tracking purposes, were also upgraded to include new air conditioning systems, painting and floor coverings.

  • Asbestos sheeting was removed from all the external faces and replaced with new Colourbond wall sheeting.
  • A new water proof membrane was installed over the entire concrete roof area.
  • New windows and doors were installed around the building.
  • The entire lighting and power system was removed and replaced with a main switchboard and multiple distribution boards. New lights and power requirements to the entire building were installed.
  • Carpets were installed and painting was done within the building.
  • A new air conditioning system was installed to both the ground floor and first floor of the building.
  • A combination of fire sprinkler and fire detection systems were installed throughout the building.
  • Minor civil works, including storm water and bitumen paving, were carried out internally

STAGE 2 REFURBISHMENT OF INFRASTRUCTURE.

Extensive building works that were carried out during Stage 2 consisted of the following:

WOOMERA VILLAGE

New road works were carried out around the shopping centre, also on the southern side of the village, where the major accommodation blocks were located. Within the sewerage treatment plant works took place to upgrade the existing plant. This consisted of repairs, sealing of cracks and building new safety handrails to provide a plant which would continue to serve Woomera for a few more years.

TECHNICAL AREA AERODROME

The main runway was closed down for a six week period whilst sections of the bitumen runway were being removed and replaced. This was due to the uneven surface causing concern to heavy planes landing at Woomera. Some demolition was carried out within hanger 3 and a new toilet block was built within the ARDU Building.

At Range 'E' a new fire diesel pump set was installed at the front entrance. This was connected to existing water storage tanks and a new fire main installed to each of the buildings. In addition a new domestic water supply was connected to each of the buildings.

All of the above works carried out by the Department of Defence are to improve the infrastructure of Woomera, which hopefully will encourage other countries to come to Australia to carry out testing.

Woomera Projects

Refurbishment of Infrastructure
Stage 1 & 2

Woomera Aerodrome
 

Project:
Woomera Refurbishment
of Infrastructure
Stage 1 & 2

Contract Sum:
$11.5m

Client:
Australian Defence Organisation

Consultant:
Graeme Coppock
KBR Consultants

 
 
       
 
    top of page » privacy » sitemap » links » home