McMahon Services - Homepage
 
     
 

PROJECT: Adelaide Central Plaza

Logos
 
 
Crushing Concrete Demolition
Cutting through concrete and steel Demolition Services
Rooftop Demolition
Demolition on all levels

The retention system originally proposed in the contract documents was replaced by a McMahon Services retention system which saved the client $500,000.

The alternative system proposed using two MPa sprayed stabilised sand in a batter and a large vertical block to retain the existing basement walls. Two MPa sprayed stabilised sand had never been used before so McMahon Services, with the supplier and subcontractor, trialled the method until a suitable mix and design was established that met the job requirements.

Large pads were excavated in the basement and poured so that the new columns for the next structure could be erected up through the basement floors before the stabilised sand was sprayed. The large pad footing incorporated some of the old footings which had large 250mm holes cored through the concrete up to 2m long to enable the new pads to be constructed.

The works were undertaken in a basement 7m below ground level with no ramp access to it. The area was extremely tight for small excavators and plant to operate in, as well as the requirement to maintain the atmosphere at a safe level so work could continue without breathing apparatus.

Adelaide Central Plaza

Redevelopment

Adelaide Central Plaza
 

Project:
Adelaide Central Plaza Redevelopment
(Former John Martins Building)

Contract Sum:
$5m

Client:
David Jones

Consultant:
Barry Phillis & Assoc.

Builder:
Hansen Yunken

       
 
    top of page » privacy » sitemap » links » home