McMahon Services - Homepage
 
     
 

ENVIRONMENT AWARDS

Logos
 
Case Awards Presentation
2004 - Case Awards Presentation
 
Liberty Towers Glenelg
Liberty Towers - Glenelg
 
Liberty Towers - Glenelg
Liberty Towers - Glenelg
 

2004 Case Earth Awards - SA Winner - Category 2

2004 SA Case Earth Awards – Liberty Towers Development

Construction Excellence: Category 2, $2 million to $10 million
South Australian winner: Liberty Towers Development
Contractor: McMahon Services Australia Pty Ltd
Principal: Baulderstone Hornibrook and Urban Construct

The Case Earth Award for Construction Excellence
To reward companies performing at the highest standards of civil construction, the Case Earth Awards recognise advancements in construction practices as well as the impact on the environment.

The selection criteria are:
1. Innovative methods
2. Industry best practice and use of new technology
3. Overcoming construction constraints and client satisfaction
4. Quality, OH&S and environmental management
5. Interface with other project parties and/or components
6. Completion within timing deadlines and cost budgets
7. Technical complexity
8. Workplace training

Judges’ comments on the winning Liberty Towers project
…a well-managed and coordinated project in very restricted conditions, addressing difficult problems such as ventilation, space limitations and a shallow groundwater table as well as delivering a cost and time efficient result…

Overview
McMahon Services’ Case Earth Award-winning task was to complete bulk earthworks for a four-level basement car park for almost 400 cars in the Liberty Towers Development in Glenelg. Liberty Towers is a 12 level residential apartment building with a total floor area of 43,500m2, making it the largest single building ever constructed in Adelaide.

The job of excavating 26,000m3 of material presented a major de-watering challenge, with the water table lying just two metres below the surface. McMahon installed a series of 6m-deep de-watering spears at the north and south elevations to lower the water table within the construction area and several holes were sunk at lift shaft locations to further lower the water table at the centre of the building. Foot valve pumps were installed to extract groundwater.

The contractors also needed to find a way to safely remove excavated material. McMahon Services used purpose-built conveyors to allow the safe transportation of materials through areas occupied by other trades. They also worked on each basement level in two halves, saving time by allowing one side to be concreted while the other was still being excavated.

Low headroom – just 2.1m – meant conventional plant and equipment could not be used, so purpose-built or modified equipment was purchased.

McMahon Services also adopted a “top down” construction method to reduce construction time. This meant installing wall panels from the existing ground level and then casting-in columns extending to the underside of the first above-ground structural floor slab. The ramp to the next level was then excavated and poured and the process repeated. The technique allowed excavation to take place under the slab at the same time as construction above it commenced.

The project budget was $1.7 million and overall completion is scheduled for September 2004.

 
awards:
case awards 2004 overview
case award category one
case awards category two
Category 2 Awards

       
 
    top of page » privacy » sitemap » links » home